Friday, January 30, 2009

30 Jan 09 New Store

It's really looking different with the drywall up. This is from around noon, and when i went in about 3pm they were nearly finished.

[image]

Thursday, January 29, 2009

This Week 29 Jan 09

Hi!

Work proceeds at the new location. The furnance on the ceiling is working and its pretty quiet, so we'll see

how long that lasts.... They are installing the insulation for the walls now, waiting for a city inspector to show up

and make sure they're doing it right. Heh.

The temporary space still has no windows, but it's no longer as cold as it was. So that's to the good. I do have

4 tables up, it's a little cramped, but shouldn't be for much longer.

Next week the new magic set comes out. The Street Date is 6 Feb, Friday, so we'll be able to have the

midnite sale Thursday nite as usual. I didnt schedule anything with Wizards because I'm not sure where we'll

be. So for now, assume that we'll be in our temp location still.


Special Orders:
MLB Risk Reinvention (n.kennedy)
WOC A&A Naval CMG Task Force B (c.brietenfeldt)

New Items:

FFG COC LCD The Spawn of the Sleeper $9.95 *2
K2D Cherry Wood Dice Tower Kit $18.00
K2D Murdero Card Game $16.00
K2D Swashbuckled $39.95
MRP COC New Tales of the Miskatonic Valley $29.95


thanks

John

Friday, January 23, 2009

New Store 23 Jan 09


Well, its been a month since i signed the lease, and we're still not in the new store. sigh. They have been working very quickly since the building permit was issued. so that's good.

Today the plumber hooked up the gas to the furnace and has started in on the restroom. Standing inside what was supposed to be the furnace room, i think i can stack the shelves a bit higher and not have to have the extra product out in the gaming area.

Plus we'll have a mop basin in the no-longer-furnace-room-but-now-a-storage-room. yay!.

[image]


Wednesday, January 21, 2009

21 Jan 09


I'm still not all that keen on the furnace being over our heads.....


[image]


Last Saturday at the New Store


With the building permit issued. everything started moving.

[image]

Tuesday, January 20, 2009

Work Proceeds, and In the Temp Space now

Ok, we are in the temp location, all squeezed in. Starting to feel a bit anxious, since im not used to working in a windowless place. Don't like it.

Ceiling has the drywall up and they were building the frame around the side and back walls. Frame for the bathroom is up, as is the frame for the heating/AC......except that they are hanging the furnace and the AC from the frikkin ceiling!

I'm kinda curious about the thinking that was involved in that. The installers werent any help. They just said thats the way the plans called for. So it looks like i have a storage room after all.

Tomorrow should be fun. I'm asking for a bid on my dividing wall and also seeing what color the ceiling and walls will be painted. I'd like offwhite for the ceiling and maybe light green or brown for the walls?

I should be putting new video tomorrow.

Wednesday, January 14, 2009

Temp Location

Starting Thursday nite and continuing thru sunday, we will be packing up the Dragon's Table and moving down the hall to Suite #103.

We'll remain open during the move, so please feel free to come and play, buy or even help pack/move.

We'll be sharing the space with GMart Comics, so it'll be pretty squeezed in, with a good chunk of product being left in packing boxes. I'm expecting we'll be in the temp location for 3-4 weeks.

I'm hoping to have room for 5-6 tables for gaming while there. It's going to be cramped, but the new space will seem like a wide limitless horizon after this.....

After explaining to the building code people that batwing saloon doors dont have latches, and hence no need for a latch safety release, we got the building permit about 2pm today.

Tomorrow they start putting the drywalll on the ceiling, and the other construction types start their work as well.

YAY!
 